Commercial roofing

Schedule roof work around a working drive-through

Use Diamond’s Tier One Nutrition job in Savannah to plan off-hours seam work, lane protection and the daily handoff back to the store manager.

What the project shows

At Tier One Nutrition in Savannah, the project record describes more than 60 leaking seams in an existing TPO roof. Diamond scheduled the work outside business hours to keep the drive-through operating. The photos show the existing surface, detailing around curbs and equipment, and the white finish. A similar business needs its own assessment of leak extent, access and operating hours.

View of blue coating around roof curbs and equipment at Tier One Nutrition.
Coating stage documented in the Tier One Nutrition project.

Price the hours that keep the lane open

  1. Give the estimator a plan showing the order point, payment window, customer queue, deliveries and where roof access is available. Identify which areas the manager can release after closing.
  2. List the windows for deliveries, preparation, coating, cleanup and reopening. Have each bidder identify any off-hours labor, repeat mobilization or equipment moves in its price.
  3. For each shift, name the person who releases the work area and the manager who accepts it back. Agree how customers will be directed if a weather change extends a closure.

Ask before approving the bid

If work cannot finish during a single closure, which section can be completed and left ready for the morning opening? Ask for the revised sequence and who calls the manager when the schedule changes.

Request an assessment

Tell us where the property is and what needs attention. Roof inspections and estimates are free, with measurements, photos, a video walkthrough and drone views included. You’ll receive a request reference number.

Add address, timing or project details (optional)