Protect a store’s receiving schedule during roof work
Bob’s Do It Best is a documented Diamond project location in Baxley. Retail owners pricing roof work can use their receiving schedule to decide where a crew should start.
Mark the stock that is hard to relocate
On the store plan, identify shelving, bulk stock and receiving space beneath the affected roof. Flag the aisles that cannot close at the same time. Provide dates for large deliveries and the name of the person who can authorize a change in unloading location.
Get an end-of-shift handoff
Ask the roofer to show which roof sections were worked, what area the next shift will need and when receiving can resume. Keep photos indexed to the store plan. If two proposals differ in how long a stockroom will be affected, ask for the difference in the work sequence to be explained before awarding the project.