Schedule roofing above a shift change
A plant entrance that looks quiet during an inspection can be the busiest point on site at shift change. Show the estimator how that affects staging.
Mark the real traffic windows
Put shift changes, break times and delivery arrivals on a single site sketch. Identify which doors workers use and which roof sections sit above them. Have the supervisor confirm the sketch before bidders visit.
Give the schedule a named owner
Ask the roofer to list the days the staging area will be occupied and the supervisor who can approve a change. Include enough notice for the next crew on shift to receive an updated route.